DCAP · PUBLIC EVIDENCEThink like engineers. Talk like fifth graders.
DATA CENTER ACCOUNTABILITY PROJECTPublic records · infrastructure · environment · community accountability
CASE 001 · PROJECT SILO

Silver Peaks. Lochbuie. Weld County.

The proposed site is in Brighton. The community story crosses city lines.

We are tracking the public records, unanswered questions and decisions around the proposed Project Silo data-center campus. Silver Peaks and neighboring Lochbuie and Weld County communities belong at the center of that story.

What would it use? Who would pay? What protections would nearby residents have? We ask for the records before treating an answer as fact.

September 28 update: Project Silo is now Case 001 of the Data Center Accountability Project. The September 26 Walk & Learn is a past event. Its materials remain part of the archive.

datacenteraccountability@pm.me

Public accountability register · Reviewed September 24, 2026

Every council question. Every answer on the record.

52 questions and document requests from three Project Silo emails are listed below. Search by topic or filter by email. Each item has a stable ID, its wording, a date field, and room for a written response and source link.

For every community

Your town can build a public record, too.

Use the free action blueprint to find the decision makers, save the documents, track unanswered questions and publish corrections.

Use the national toolkit
Community Ledger · September 25

What changed, and what still needs an answer

A dated blog for Project Silo records, accountability updates and a blueprint for other communities. Subscribe by RSS now; a consent-based daily email list is being prepared.

Neighbors showing up

Thank you to Adams County DSA, Bridge to Brighton, the Silver Peaks HOA, and Stacey Baca Reports for bringing attention and care to this issue. . This is an independent project; thanks do not imply these groups or people endorse every statement on this site.

Project Silo / Willard Property
NEIGHBORHOODS MATTER. COMMUNITY MATTERS. NEIGHBORS MATTER.

Follow the
paper trail.

A source-first public archive for the records, questions, official responses, meetings and reporting surrounding a proposed data-center campus in northeast Brighton.

Project-owner campaign statement“NO DATA CENTERS IN OUR NEIGHBORHOODS.”
COLORADO STRONG · COMMUNITY FIRST · FACTS BEFORE POLITICS
Record note
Do not confuse transformer nameplate ratings with actual campus demand. The electrical concept depicts four transformers labeled 200 MVA; the archive treats actual peak MW, annual MWh and interconnection details as unanswered until documented.
Why location matters

Residential communities are part of the record.

Silver Peaks is a residential community in Lochbuie. Jacob's Run is a recognized Brighton subdivision. The archive is seeking official GIS/setback records for exact distances between Project Silo and nearby homes. A claimed “200-yard” separation and a Brighton-area “Fox Run” connection are not published here as facts because they have not yet been independently verified.

From the record

What the documents actually say

These entries are written narrowly. They describe what a dated source says, not what anyone should conclude about the project.

Jan. 29, 2025
City PAC record

Several large data-center buildings were discussed.

Brighton's pre-application notes describe a data center with several approximately 300,000-square-foot buildings, a switching station and substation.

Source
Jun. 27, 2025
Concept plan

The Silo concept plan identifies data-center and switching-station areas.

The plan is expressly illustrative and conceptual and says the design may change with project development and the actual end user.

Source
Jul. 31, 2025
City PAC record

Traffic, drainage and water-resource work remained part of review.

City comments say a Traffic Impact Study would be required if one did not already exist, raw water would need to be dedicated and a water-resource report would be required.

Source
Exhibit · 06.27.25Silo concept plan source-document preview
Source preview only. Open the original PDF in the document archive for the authoritative record.
Why this archive exists

One place for the source material.

01

Original documents

Public-record PDFs stay available alongside summaries so readers can inspect the record themselves.

02

Questions in writing

Technical and process questions are logged, dated and paired with responses when they arrive.

03

Reporting is labeled

News coverage is linked to the publisher and identified as outside reporting rather than presented as a City record.

04

Corrections leave a trail

If a fact changes or proves wrong, the correction is documented instead of quietly rewriting the archive.

Open questions

What still needs an answer

The issue register keeps the focus on measurable information and documented process.

01 / POWER

Actual electrical demand

Peak MW, annual MWh, serving utility, interconnection status and who pays for required infrastructure.

02 / WATER

Cooling & water use

Average, peak and annual use; cooling technology; source; recycling; raw-water dedication and drought assumptions.

03 / COMMUNITY

Noise, light & proximity

Nighttime dBA/dBC, low-frequency and tonal analysis, photometrics, buffers and distances to homes and schools.

04 / PROCESS

Moratorium & pending status

Whether a pause would cover Project Silo, and whether any vested-rights, grandfathering or pending-application exception is claimed.

Outside coverage

Reporting, linked to the source

We do not re-host news footage or copy full articles. We link readers to the publisher.

Denver7 · Sept. 23, 2026

Brighton residents uncover proposal for massive data center campus, spurring potential moratorium

Denver7 reports on Project Silo and Mayor Pro Tem Peter Padilla's stated plan to propose a 90-day moratorium.

Read Denver7
Coming to the studio

Weekly audio for neighbors and the nation

We are preparing a source-linked podcast on Project Silo, the council questions, and the decisions that other communities also face. The first episode is being planned; no recording is posted yet.